Current Projects
| Summer 2026 Capital Projects | Affected Areas | Timeline | Current Status |
|---|---|---|---|
| Site Drainage and Paved Paths Improvements | Bldgs. 5, 6, 7, 8, & 10, Campus Green | June 22 - Completion | Ongoing |
| Bldg. 10 Flooring Repair & Refresh | Bldg. 10 | June 21 - Sept. 18 | Ongoing |
| Bldg. 11 Remodel & Repairs | Bldg. 11 | June 28 - Sept. 10 | Ongoing |
Site Drainage and Paved Paths Improvements | Starting Jun. 22
Affected Areas
What to Expect
- During construction, temporary pedestrian detours will be in place as pavement is removed, repaired and replaced. Detour signage will be posted throughout the project.
- The pathway along the south side of Bldg. 6 is expected to remain closed for the duration of the work. Construction will be completed in phases to maintain safe access to the front entrance of Bldg. 5 whenever possible. Bldg. 5 will also remain accessible through its north entrance, which avoids the construction area.
- The ADA parking spaces at the front entrance of Bldg. 5 will be temporarily closed for contractor staging and to allow reconfiguration of the spaces to meet current ADA standards.
- Contractors will access the work site through Employee Parking Lot 12. As a result, parking lot access and traffic flow may be temporarily affected.
Impacted Occupants: Bldgs. 5 & 6
Bldg. 10 Bremer Student Center Flooring Repair and Refresh | June 21 - Sept 18
This message is to inform you of an upcoming capital improvement project in Bldg. 10, the Bremer Student Center. The project will include replacement of damaged flooring, refresh of interior finishes and repainting of designated areas.
Because the project area includes multiple staff offices and workspaces, these areas will be inaccessible during construction. Employees whose workspaces are affected will need to relocate to alternative work sites or make other temporary work arrangements during the construction period.
Displacement Timeline | June 21 - Sept. 18
- June 21 - 25: Transition week for packing, moving, and preparing affected spaces for construction.
- June 28: Contractor begins work in vacated areas.
- Sept. 11: Construction is expected to be substantially complete.
- Sept. 14 - 18: Move-in period for returning furniture, reconnecting and setting up IT equipment, and reoccupying workspaces.
Alternate Work Areas
- Hideko Lyle and Rodgie Oliver (Multicultural Office), Peer Mentors and OCAB - Bldg. 4, Rm. 312 & Bldg. 10 Upper Lounge
- Rachel Leeper (International Office) - Bldg. 4, Rm. 203I
- Tony Coolidge (International Office) - Bldg. 4 Rm. 204B
- Bailey Sarto, Matt Merritt, and Lynzey Gotchall (Athletics) - Bldg. 10, Rm. 017
- Josh Lane and Li-Neishin Co (Well-Being and Health Promotion) - Remote & Bldg. 12, Rm. 114
- Cody Rodgers (Title IX) - Remote
- David Keith Huntzinger (Adjunct Faculty) - Bldg. 4, Adjunct Faculty Office
Additional information regarding relocation logistics and workspace arrangements will be shared with affected departments as planning progresses.
Bldg. 11 Remodel & Repairs | June 28 – Sept. 18
Military and Veterans Program Lounge Closure
The Military & Veterans Program Lounge will be inaccessible during construction. Employees who work in this area will need to make alternative workspace arrangements during the project.
Displacement Timeline | June 28 - Sept. 18
June 28 – July 3: Transition week for packing and preparing workspaces for relocation.
July 6: Construction begins in the vacated areas.
Sept. 11: Construction is expected to be substantially complete.
Sept. 14 – 18: Move-back period for furniture, IT equipment and workspace setup.
Impacts to Bldg. 11 Occupants
(Military & Veteran Programs, Communications Department and Western Washington University)
Employees working elsewhere in Bldg. 11 should be aware of the following potential impacts:
Temporary Office Access Restrictions: Certain offices may be inaccessible for short periods while hallway flooring is replaced. If this work proceeds, access disruptions may total approximately six days, potentially split into separate phases. Specific dates will be communicated once finalized.
Restroom Closures: Bldg. 11 restrooms will be closed throughout the construction period, from July 6 through Sept. 11. Employees should plan to use restrooms in adjacent Bldgs. 10, 12 or 14.
Construction Activity: Occasional construction noise, odors and temporary detours at building entrances should be expected during the project.
Contact your supervisor regarding workspace arrangements.